Short Answer
What is the planned-order release using an MRP program if the gross requirement is 1,600 and the inventory on hand is 600? ______________________________
Correct Answer:

Verified
1,000
Explanation: 1,600 - 600 = 1,000.U...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
1,000
Explanation: 1,600 - 600 = 1,000.U...
Explanation: 1,600 - 600 = 1,000.U...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Related Questions
Q30: Which of the following is the planned-order
Q36: The master production schedule states the number
Q37: MRP is a logical, easily understandable approach
Q42: A BOM file is often called a
Q45: A master production schedule is an input
Q55: The time-phased plan specifying how many and
Q57: A modular bill-of-materials is the term for
Q58: What is the name for a bill
Q61: Which of the following is not a
Q65: A modular bill-of-materials includes items with fractional