Multiple Choice
You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:

Verified
Correct Answer:
Verified
Q7: You have just performed a CPM analysis
Q32: A simple project listing of five activities,
Q33: Describe how CPM handles the trade-offs between
Q36: A matrix project attempts to blend properties
Q38: A company must perform a maintenance project
Q39: You have the following time and cost
Q40: PERT is an abbreviation for which of
Q43: In a Gantt chart, the horizontal axis
Q99: An advantage of a pure project where
Q100: One of the assumptions made using CPM