Multiple Choice
PERT is an abbreviation for which of the following methodologies?
A) Product evaluation, result, and treatment
B) Programming and evaluation realization technology
C) Program evaluation and review technique
D) Process evaluation and review technology
E) It is a name, not an abbreviation for anything.