Multiple Choice
In a Cost of Quality (COQ) framework, rework costs incurred before shipment of product are considered:
A) Internal failure costs.
B) Retention costs.
C) Appraisal costs.
D) Prevention costs.
E) External failure costs.
Correct Answer:

Verified
Correct Answer:
Verified