Evaluate the Following Project Using an IRR Criterion,based on an Opportunity

Question 45

Multiple Choice

Evaluate the following project using an IRR criterion,based on an opportunity cost of 10%: C0= -6,000,C1= +3,300,C2= +3,300.


A) Accept, since IRR exceeds opportunity cost.
B) Reject, since opportunity cost exceeds IRR.
C) Accept, since opportunity cost exceeds IRR.
D) Reject, since IRR exceeds opportunity cost.