Solved

If the Expected Length of a Path Is More Than

Question 50

True/False

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path would not be a factor in assessing the probability of finishing the project on time.

Correct Answer:

verifed

Verified

Unlock this answer now