menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Study Set 1
  4. Exam
    Exam 17: Project Management
  5. Question
    What Is the Probability That the Critical Path for This
Solved

What Is the Probability That the Critical Path for This

Question 45

Question 45

Multiple Choice

What is the probability that the critical path for this project will be completed within 200 days?


A) 0.8413
B) 0.9544.
C) 0.9772
D) 0.9974
E) 0.9987

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q40: What is the total cost of reducing

Q41: Project management differs from management of more

Q42: Prepare a crashing plan for the following

Q43: What is the estimated slack time for

Q46: The optimum project length in crashing occurs

Q47: What is the estimated expected (mean) time

Q48: Consider the project depicted by the following

Q49: What is the estimated expected (mean) time

Q50: If the expected length of a path

Q101: The standard deviation of the critical path

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines