Multiple Choice
Project management differs from management of more traditional activities mainly because of:
A) its limited time frame
B) its unique, defined set of activities
C) (a) and (b)
D) the requirement for use of the appropriate resources
E) the need for planning and execution
Correct Answer:

Verified
Correct Answer:
Verified