A time study of a job produced the following: average cycle time = 1.5 minutes, performance rating = 1.15. Allowances are 18 percent of the workday (480 minutes). Determine the standard time for this job.
Correct Answer:

Verified
\[\begin{array} { l l }
\mathrm { OT } ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
\mathrm { OT } ...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q24: One potential disadvantage of self-directed teams is
Q26: A methods and measurements analyst for
Q27: A behavioral approach to job design which
Q32: When performing a time study, the analyst
Q33: A work sampling study of kitchen
Q38: A major advantage of job specialization in
Q46: The standard time for a job can
Q84: A performance rating of less than 1.0
Q106: A worker-machine chart can help identify nonproductive
Q174: A simo chart includes:<br>A)delay.<br>B)storage.<br>C)transportation.<br>D)left/right hand movements.<br>E)inspection.