A time study of a job produced the following: average cycle time = 1.5 minutes, performance rating = 1.15. Allowances are 18 percent of the workday (480 minutes). Determine the standard time for this job.

Correct Answer:

verifed

Verified

\[\begin{array} { l l }
\mathrm { OT } ...