Multiple Choice
A production line is to be designed for a job with three tasks.The task times are 0.3 minutes, 1.4 minutes, and 0.7 minutes.The minimum cycle time in minutes is:
A) 0.3
B) 0.7
C) 1.4
D) 2.4
E) 0.8
Correct Answer: