Multiple Choice
In monitoring project time (schedule) performance, actual performance should be compared to
A) Budgets for the current year.
B) Top management's targets.
C) Project network schedule derived from the WBS/OBS.
D) Progress on similar past projects.
E) Previous status reports.
Correct Answer: