Baseline Project Budgets Are Derived from

Question 11

Multiple Choice

Baseline project budgets are derived from


A) The organization's overall budget.
B) Time-phasing the work packages.
C) Top management directions.
D) The total direct, direct project overhead and G&A overhead costs.
E) The earned value system.

Correct Answer: