Multiple Choice
The method most frequently used in measuring project progress is the
A) 0/100 percent rule
B) 75/25 percent rule
C) 50/50 percent rule
D) 25/75 percent rule
E) Percent complete rule
Correct Answer:

Verified
Correct Answer:
Verified