Multiple Choice
An index value less than one indicates that the project is
A) Under cost or behind schedule
B) Over cost or ahead of schedule
C) Under cost or ahead of schedule
D) Over cost or behind schedule
E) On cost or on schedule
Correct Answer:

Verified
Correct Answer:
Verified