Multiple Choice
Which of the following will calculate the estimated cost to complete the project?
A) (VAC-EV) /(PV/AC)
B) (BAC-EV) /(EV/AC)
C) (PV/AC) /(VAC-EV)
D) (EV/AC) /(BAC-EV)
E) (BAC-EV) /(BAC-AC)
Correct Answer:

Verified
Correct Answer:
Verified