The Last Step in the Project Control Process of the Measurement

Question 16

Multiple Choice

The last step in the project control process of the measurement and evaluation of project performance is to:


A) Take appropriate action
B) Prepare a report to top management
C) Follow up on corrective action
D) Measure progress and performance
E) Review spending with team members

Correct Answer: