Multiple Choice
Which of the following is/are included in a Project Cost-Duration Graph?
A) Total indirect cost
B) Total direct cost
C) Total project cost
D) Both A and B are correct
E) A, B, and C are all correct
Correct Answer:

Verified
Correct Answer:
Verified