The most common response for meeting unattainable deadlines is to
A) Reduce or scale back the scope of the project.
B) Decrease the critical paths
C) Crash all elements of the project
D) Change the time to market statement
E) B, and C are correct
Correct Answer:

Verified
Correct Answer:
Verified