menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Reducing Project Duration
  5. Question
    Subtracting an Activity's Normal Cost from the Crash Cost Will
Solved

Subtracting an Activity's Normal Cost from the Crash Cost Will

Question 81

Question 81

Short Answer

Subtracting an activity's normal cost from the crash cost will calculate an activity's ________.

Correct Answer:

verifed

Verified

rise
Expla...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: Shortening an activity's duration is termed crashing.

Q52: When considering whether to move the project

Q61: An activity's _ is calculated by dividing

Q77: The most common response for meeting unattainable

Q78: Given an equal level of risk and

Q79: Identify options for accelerating a project schedule

Q82: Because direct costs are assumed to be

Q83: Project costs are generally classified as _

Q84: Direct costs are assignable directly to a

Q86: Creating a Project Cost-Duration Graph in the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines