Multiple Choice
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a _________ constraint.
A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
Correct Answer:

Verified
Correct Answer:
Verified