Multiple Choice
The backward pass in project network calculations determines the
A) Latest time's activities can begin
B) Earliest time's activities can be finished
C) Critical path
D) Both A and C are correct
E) A, B, and C are all correct
Correct Answer:

Verified
Correct Answer:
Verified