Burst activities have more than one activity immediately following it (more than one dependency arrow flowing from it).

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q34: The WBS identifies dependencies, the sequencing of

Q35: _ can never be negative and applies

Q40: Identify and briefly describe the four types

Q78: Which of the following is not one

Q81: A _ activity is frequently used to

Q83: In a project network, _ (recycling through

Q85: The backward pass in project network calculations

Q86: What is a lag and why would

Q87: A(n) _ is an element in the

Q105: Only activities that occur at the end

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines