The minimum amount of time a dependent activity must be delayed to begin or end is referred to as


A) Hammock.
B) Laddering.
C) Lag.
D) Cushion.
E) Buffer.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q55: Briefly describe looping and conditional statements and

Q75: Within an Activity-on-Node network, the arrows depict

Q84: Arrows on an activity-on-node (AON)project network represent<br>A)An

Q85: Activities that must immediately follow a given

Q86: A(n)_ activity is frequently used to identify

Q89: A(n)_ calculates project duration.

Q90: _ reflects the likelihood the original critical

Q91: The _ lag is the most typical

Q92: An activity can include only one work

Q116: When completing a forward pass, you carry

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines