When completing a forward pass, you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity. In this case you select the largest early finish number of all its immediate predecessor activities. Why do you select the largest early finish number?
Correct Answer:

Verified
Acknowledging that the finish number rep...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q111: What is a Gantt chart and what
Q112: Consider the following table of activities A
Q113: Which of the following is true about
Q114: In developing a project network, neither looping
Q115: Which of the following correctly calculates the
Q117: When an activity with a long duration
Q118: Consider the following table of activities A
Q119: Which of the following will correctly calculate
Q120: What is a lag and give an
Q121: Consider the following table of activities A