menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 6: Developing a Project Plan
  5. Question
    A (N) ________ Represents a Point in Time When an Activity
Solved

A (N) ________ Represents a Point in Time When an Activity

Question 52

Question 52

Short Answer

A (n) ________ represents a point in time when an activity is started or completed and does not consume time.

Correct Answer:

verifed

Verified

event
Explanation: Event is us...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: What is the Concurrent Engineering Approach and

Q31: The critical path is the shortest path

Q48: Which of the following will correctly calculate

Q50: By definition, the critical path always has

Q53: An activity is on the critical path

Q54: An AON project network uses which of

Q56: Using a special color copy machine for

Q57: Concurrent engineering is a good example of

Q58: Different activities along the same path can

Q87: The minimum amount of time a dependent

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines