Short Answer
A (n) ________ represents a point in time when an activity is started or completed and does not consume time.
Correct Answer:

Verified
event
Explanation: Event is us...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
event
Explanation: Event is us...
Explanation: Event is us...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge