menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    The Critical Path Is the Shortest Path Through a Network
Solved

The Critical Path Is the Shortest Path Through a Network

Question 31

Question 31

True/False

The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q26: After the total slack for each activity

Q27: A project manager is building a project

Q28: The minimum amount of time a dependent

Q29: It is acceptable for arrows to cross

Q30: If the project has a duration of

Q32: The amount of delay within a task

Q33: Consider the following table of activities A

Q34: The WBS identifies dependencies, the sequencing of

Q35: Identify the four types of lags giving

Q36: Which of the following represents an activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines