Companies like Boeing, Kodak, and IBM are using which of the following for improving the estimating process?
A) Adjusting estimates based on individual forecasting abilities
B) Benchmarking using the experience of other companies
C) Using time and motion studies
D) Creating historical databases of previous projects
E) All of these are correct
Correct Answer: