Question 21
Short Answer
The salary of the project manager and temporary rental space for the project team would be classified as ________ costs.
Question 22
Short Answer
The ________ method for estimating project time and cost uses weighted variables based on major parameters and is frequently used in the development of software.
Question 23
True/False
If time and costs are important to a project the top-down approach to estimating time and costs for the project is the best choice.
Question 24
Multiple Choice
Which of the following is a good condition for bottom-up estimating?
Question 25
Multiple Choice
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.Which of the following methods is he using?
Question 26
Multiple Choice
Typical kinds of costs found in a project include
Question 27
Multiple Choice
A good starting point for developing time and cost estimates is
Question 28
True/False
The use of past experience is almost always used primarily in the initial phases of a project.
Question 29
True/False
Phase estimating uses both the bottom-up and top-down methods for estimating project time and costs.
Question 30
Essay
Why are the estimates for a project's time and costs important for all phases of a project?
Question 31
Short Answer
Using the ________ method of forecasting project time and costs is the preferred method for situations where the cost and time estimates are important, in a fixed contract situation, and when the customer wants a lot of detail.