    The Intersection of the WBS and the OBS Is Called
Solved

The Intersection of the WBS and the OBS Is Called

Question 19

Question 19

Multiple Choice

The intersection of the WBS and the OBS is called the


A) Responsibility matrix
B) Priority matrix
C) Work package
D) Cost account
E) Project overlap

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: The most detailed element in the hierarchical

Q15: The primary purpose of the first step

Q16: If a project is small or of

Q17: Scott has just been given a project

Q18: A(n) _ is a grouping of work

Q20: What is a Project Priority Matrix and

Q21: The most commonly used method for coding

Q22: The hierarchical work breakdown structure can be

Q23: The Snapshot from Practice dealing with Big

Q24: The process of assigning specific work packages

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines