Multiple Choice
If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?
A) Responsibility matrix
B) Organization breakdown structure
C) Work breakdown structure
D) Priority matrix
E) Process breakdown structure
Correct Answer:

Verified
Correct Answer:
Verified