Multiple Choice
Bill is working on a project involving the upgrading of a management information system.The project is being managed by the information systems department with coordination with other departments occurring through normal channels.He is working in a _________ organization.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
Correct Answer:

Verified
Correct Answer:
Verified
Q8: In a balanced matrix form of project
Q23: The relationship between the Apple II and
Q24: The Macintosh development team at Apple is
Q25: The matrix form of project management structure
Q26: Matrix management is a hybrid organizational form
Q27: Who is responsible for determining how tasks
Q27: Organization _ refers to a system of
Q32: "Projects are a smaller version of the
Q33: In the projectized form of company organization
Q86: The functional project team is usually physically