Multiple Choice
Who is responsible for determining how tasks will be done in a matrix project management structure?
A) The functional manager
B) The project manager
C) Both are responsible
D) This is no pattern of who takes responsibility
E) None of these are true
Correct Answer:

Verified
Correct Answer:
Verified