Multiple Choice
Newbill Enterprises recently used 24,000 labor hours to produce 8,600 completed units.According to manufacturing specifications,each unit is anticipated to take 2.75 hours to complete.The company's actual payroll cost amounted to $456,000.If the standard labor cost per hour is $19.20,Newhart's labor rate variance is:
A) $1,920U.
B) $1,920F.
C) $4,800U.
D) $4,800F.
E) None of thesE.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The following information for a recent project
Q4: Justin Company recently purchased materials from a
Q5: Upstart,Inc.manufactures a product that has the following
Q6: The manufacturing cycle efficiency for PQR Company
Q8: The standard hours allowed for the work
Q11: A direct-labor efficiency variance cannot be caused
Q12: The direct-labor efficiency variance is:<br>A)$7,000F.<br>B)$7,000U.<br>C)$7,100F.<br>D)$7,100U.<br>E)None of thesE.<br>
Q30: A statistical control chart is best used
Q56: Which of the following individuals is least
Q85: An unfavorable labor efficiency variance is created