Multiple Choice
The manufacturing cycle efficiency for PQR Company when the processing time is six hours and inspection,waiting,and move time are one hour each is:
A) 0.67.
B) 0.75.
C) 0.78.
D) 0.88.
E) an amount other than those shown abovE.
Correct Answer:

Verified