Multiple Choice
What is an auditor's evaluation of a statistical sample for attributes when a test of 100 documents results in four deviations if the tolerable rate of deviation is 5%,the expected population deviation rate is 3%,and the allowance for sampling risk is 2%?
A) Accept the sample results as support for planned reliance on the control because the tolerable rate of deviation less then allowance for sampling risk equals the expected population deviation rate.
B) Modify planned reliance on the control because the sample rate of deviation plus the allowance for sampling risk exceeds the tolerable rate of deviation.
C) Modify planned reliance on the control because the tolerable rate of deviation plus the allowance for sampling risk exceeds the expected population deviation rate.
D) Accept the sample results as support for planned reliance on the control because the sample rate of deviation plus the allowance for sampling risk exceeds the tolerable rate of deviation.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: In performing tests of controls over authorization
Q29: Which of the following statements is correct
Q30: The sample rate of deviation is determined
Q31: The expected population deviation rate has a(n)_
Q32: As a result of tests of controls,an
Q33: The difference between the sample rate of
Q35: Which of the following steps in the
Q36: The _ is the maximum rate of
Q37: If an audit team calculated an upper
Q39: An auditor interested in ensuring that all