Multiple Choice
If an audit team calculated an upper limit rate of deviation of 5 percent when the tolerable rate of deviation was 4 percent,both at the same risk of overreliance,control risk should be
A) Assessed at the level associated with the 4 percent tolerable rate of deviation.
B) Increased and substantive procedures should be adjusted accordingly.
C) Assessed at the maximum level (100 percent) because the company's performance failed the test.
D) Decreased and substantive procedures should be adjusted accordingly.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: In performing tests of controls over authorization
Q32: As a result of tests of controls,an
Q33: The difference between the sample rate of
Q34: What is an auditor's evaluation of a
Q35: Which of the following steps in the
Q36: The _ is the maximum rate of
Q39: An auditor interested in ensuring that all
Q40: Using the appropriate sampling tables,fill in the
Q42: The primary benefit of using nonstatistical sampling
Q90: In the study of internal control,the auditor