Which of the Following Is Responsible for the Continued Support

Question 10

Multiple Choice

Which of the following is responsible for the continued support of consistent application of selection criteria,standards,processes,training,and general assistance to project managers and continued improvement and use of best practices?


A) Portfolio project management
B) Project office
C) Project management
D) Oversight committee
E) Resource allocation optimization committee