The Level of the Project Management Maturity Model Where There

Question 11

Short Answer

The level of the Project Management Maturity Model where there is an organizationwide project management system that is tailored to the needs of the organization is called ____________ of project management.

Correct Answer:

verifed

Verified

institutionalization
Explanation: In Lev...