Multiple Choice
Sally receives the following information on her project: PV = 100, AC = 75, EV = 100.How well is the project doing in terms of budget?
A) Right on budget
B) 25 under budget
C) 25 over budget
D) 50 under budget
E) 50 over budget
Correct Answer:

Verified
Correct Answer:
Verified