Which of the Following Are Required to Assess the Current

Question 34

Multiple Choice

Which of the following are required to assess the current status of a project using the earned-value cost / schedule system?


A) BAC, EAC, and ETC
B) VAC, EAC, and BAC
C) CV, SV, and BAC
D) PV, EV, and AC
E) TCPI, EV, and PV

Correct Answer: