    An Activity's Normal Time and Cost Are 8 and $100,respectively
Solved

An Activity's Normal Time and Cost Are 8 and $100,respectively

Question 42

Question 42

Multiple Choice

An activity's normal time and cost are 8 and $100,respectively.Its estimated crash time and cost are 6 and $160,respectively.What is this activity's crash cost per time unit?


A) $33
B) $30
C) $60
D) $65
E) $153

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q21: When you schedule _, you avoid the

Q30: According to _ law, adding more manpower

Q32: Given an equal level of risk and

Q40: All of the following are disadvantages of

Q48: Brooks' law states that adding manpower to

Q54: Intense global competition and rapid technological advances

Q65: Reducing the duration of an activity is

Q74: When project managers know an activity's _,

Q100: Which of the following correctly calculates an

Q104: Overhead costs such as supervision, administration, consultants,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines