Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by
A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Correct Answer:

Verified