Multiple Choice
Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.
A) Normal
B) Budgeted
C) Optimized
D) Expected
E) Targeted
Correct Answer:

Verified
Correct Answer:
Verified