Multiple Choice
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?
A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality
Correct Answer:

Verified
Correct Answer:
Verified