menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 2
  4. Exam
    Exam 9: Reducing Project Duration
  5. Question
    The Direct Cost for Completing an Activity as Early as Possible
Solved

The Direct Cost for Completing an Activity as Early as Possible

Question 2

Question 2

Short Answer

The direct cost for completing an activity as early as possible is called its ________ cost.

Correct Answer:

verifed

Verified

Related Questions

Q4: Reducing project duration<br>A)Involves crashing all activities to

Q5: One way of reducing project costs is

Q6: Intense global competition and rapid technological advances

Q8: Direct costs are assignable directly to a

Q10: Insensitive networks are a rarity; Planning for

Q10: Costs such as labor, materials, equipment, or

Q11: The shortest possible time an activity can

Q28: When determining which activity to crash, there

Q32: Given an equal level of risk and

Q35: Shortening an activity's duration is termed crashing.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines