Multiple Choice
The chances of a risk event occurring as a project proceeds through its life cycle tend to
A) Slowly rise.
B) Drop sharply and then level out.
C) Rise sharply and then level out.
D) Remain about the same.
E) Slowly drop.
Correct Answer:

Verified
Correct Answer:
Verified