The Chances of a Risk Event Occurring as a Project

Question 67

Multiple Choice

The chances of a risk event occurring as a project proceeds through its life cycle tend to


A) Slowly rise.
B) Drop sharply and then level out.
C) Rise sharply and then level out.
D) Remain about the same.
E) Slowly drop.