menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 2
  4. Exam
    Exam 6: Developing a Project Plan
  5. Question
    A(n)________ Is the Minimum Amount of Time a Dependent Activity
Solved

A(n)________ Is the Minimum Amount of Time a Dependent Activity

Question 24

Question 24

Short Answer

A(n)________ is the minimum amount of time a dependent activity must be delayed to begin or end.

Correct Answer:

verifed

Verified

lag
Explanation: A lag is the ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: Which of the following is NOT one

Q6: If, for some reason, the project must

Q19: After the total slack for each activity

Q25: On a project network, the activity times

Q39: An activity cannot begin until ALL preceding

Q54: It is possible for a project network

Q56: In the network computation process what is

Q77: System documentation cannot end until three days

Q81: What is a hammock activity and give

Q119: Which of the following will correctly calculate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines