Multiple Choice
Which of the following will correctly calculate the total slack in an activity?
A) LS - ES
B) LF - EF
C) LS - LF
D) LF - ES
E) Either LS - ES or LF - EF
Correct Answer:

Verified
Correct Answer:
Verified