Which of the following does NOT help describe a bottom-up estimating approach?
A) They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.
B) They establish low-cost, efficient methods for completing activities.
C) They typically comes from the people actually doing the work and who are most knowledgeable about the task at hand.
D) Estimates are made at the work package level and then "rolled up" to determine estimates for major deliverables and for the project itself.
E) They can take place after the project has been planned in detail.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The project management structure chosen to manage
Q8: The top-down method of estimating when the
Q12: Rose is working on estimates for a
Q14: When someone uses experience and/or information from
Q16: Identify and briefly describe the two major
Q19: Which of the following is NOT one
Q38: If a project is internal to the
Q54: Work package estimates should include allowances for
Q66: Which of the following is a good
Q95: Identify the three major categories of project