Which of the Following Is a Good Condition for Bottom-Up

Question 66

Multiple Choice

Which of the following is a good condition for bottom-up estimating?


A) When the project involves strategic decision making
B) When the project is internal and small
C) When there is a fixed price contract
D) When there is high uncertainty involved in the project
E) When there is an unstable scope

Correct Answer: